Task Id |
Task Name |
Resource |
Task Start |
Task End |
Percent Complete |
Dependencies |
1
|
Window installation
|
installation
|
2020-01-22
|
2020-01-30
|
100
|
NULL
|
2
|
Electrics
|
NULL
|
2020-02-01
|
2020-02-15
|
100
|
1
|
3
|
Plumbing works
|
NULL
|
2020-02-10
|
2020-03-09
|
100
|
1
|
4
|
Doorway reconstruction
|
NULL
|
2020-03-10
|
2020-03-26
|
40
|
3
|
5
|
Leveling the walls
|
leveling
|
2020-03-14
|
2020-04-14
|
10
|
2,3,4
|
6
|
Leveling the ceilings
|
leveling
|
2020-03-18
|
2020-04-28
|
100
|
2,3,4
|
7
|
Leveling the floor level
|
leveling
|
2020-03-22
|
2020-04-24
|
35
|
2,3,4
|
8
|
Painting of ceilings
|
painting
|
2020-04-25
|
2020-05-05
|
0
|
5,6,7
|
9
|
Painting of walls
|
painting
|
2020-05-06
|
2020-05-21
|
0
|
8
|
10
|
Installation of flooring
|
installation
|
2020-05-22
|
2020-07-01
|
0
|
9
|
11
|
Door installation
|
installation
|
2020-07-02
|
2020-07-22
|
0
|
10
|